Extension.

This is a single storey extension, with a flat roof and concrete detailed copings.

After digging out and stoning up, a raft foundation was required with a toe. As you can see the reinforcing bars had to be tied to suit this detail.

This shows the edge detail of the reinforcing bars.

To complete the base ready for concreting, a solid timber shuttering was required.

The completed base ready for concreting.

Concreting.

The finishing touches to concreting.

The raft after the concrete had cured.

The shuttering has been removed showing the step in the raft foundation. All loaded out ready to start the brick and block work.

Brick and block work well on the way, with the joists fitted too.

Just completing the brick and block work to form the parapit wall and fitting the stone detailed copings.

All the copings and brick work complete.

Front view of the extension.

Plastering has been completed, dpm barrier and floor insulation been fitted.

Chipboard flooring being installed.

Just putting the finishing touches too the extension.


The Complete project.


 